MODERNISATION OF THE RAILWAY LINE OF THE NORTH – SUB-SECTION 3.1

Client: REFER – Rede Ferroviária Nacional, E.P.
Location: Pampilhosa/Quintans – Portugal
Execution Period: 52 Months

 

Execution of infrastructures and superstructures of track and overhead contact line (catenary). Construction and remodelling of railway stations and construction of overpasses, underpasses and culverts in the Railway Line of the North, between Pampilhosa and Quintans.

Double Track
Design speed: 220 km/h
Catenary type LP5
Railway track works: 68 km
Overhead Contact Line: 66 km

Vegetation clearing: 257.370 m2
Stripping: 257.370 m2
Excavation for backfill with soils from the project: 134.696 m³
Excavation for soils storage: 97.074 m³
Current backfill: 86.439 m³
Platform capping with Ø 0,20 m – quarry run: 48.526 m³
Geotextile in backfills: 30.055 m2
Fence type C (progressive mesh): 58.380 m
Triangular precast concrete ditches with cover: 15.830 m
Geodrain Ø 200 mm: 26.923 m
Geodrain Ø 300 mm: 6.124 m
Concrete manholes with height inferior to 2,5 m and sink: 96 units
Concrete manholes with height inferior to 2,5 m without sink: 1.116 units

 

Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.

Strictly Necessary Cookies

Strictly Necessary Cookie should be enabled at all times so that we can save your preferences for cookie settings.

3rd Party Cookies

This website uses Google Analytics to collect anonymous information such as the number of visitors to the site, and the most popular pages.

Keeping this cookie enabled helps us to improve our website.