Detalhes do Projeto
REHABILITATION OF THE RAILWAY BRANCH OF THE PORT OF SINES
Client: APS – Administração dos Portos de Sines e do Algarve, S.A.
Location: Terminal XXI – ZIL3 – TCS Terminal Contentores Sines – Portugal
Execution Period: 9 Months
The works carried out in the railway branch of the port of Sines was part of the intervention to broaden the capacity of the reception / expedition hub, giving the said branch a higher capacity and performance and allowing for the operation of 750 m long trainsets. The main alterations to be introduced were the re-adjustment of the western side of the reception / expedition hub – in particular Line I that was given a length compatible with the operation of 750 m long trainsets; the creation of a 4th in the existing reception / expedition hub, parallel to Line III, with capacity to operate trainsets with the said length; the creation of the necessary infrastructure to allow, in the future, for the construction of a 5th Line, parallel to Line IV; the creation of a new access line that, beginning at the existing one will make it possible to connect to the new loading / unloading zone of the existing Terminal ; the creation of a connection the east end of the reception hub and the new access line; the creation of a new reversion end to replace the existing one; the creation of a new siding end to park rolling stock; and also the insertion of a TJD (transversal double junction) allowing for the connection between (siding / reception hub) and the future access lines and reversion line, as well as to the siding line.
Main work quantities:
Earthworks and Paving:
Earthworks: 97.930 m³
Sub-ballast: 3.650 m³
Drainage:
Ditches, trenches, half-round, drains and collectors: 8.935 m
Drainage boxes and discharge outlets: 80 units
Accessory Works:
Landscaping – Hydroseeding in two applications: 14.800 m2
Fences in variable wire mesh: 1.200 m
Public lighting networks and lighting columns / towers; Infrastructure: 2.200 m
Reinforced concrete walls and track buffer stop: 365 m³
Signage and Safety Equipment:
Trenches and crossings with cable trays in prefabricated gutter / PEHD pipes: 4.960 m
Earthing network: 3.980 m
Railway track:
Track UIC 54/ wood sleeper removal: 1.008 m
Supply and laying of track with 54E rail and multi-purpose monoblock sleepers: 2.211 m
Supply and laying of railroad switchers: 7 units
Supply of ballast and track ballasting: 12.000 tons
Heavy mechanical tamping, including dynamic stabilisation in open track: 6.194 m
Execution of aluminothermic welding in open track and TSD (track switching devices): 376 units
Levelling of long welded bar: 12.012 m
Track Electrification:
Civil Works: Concrete in foundation footings and poles sealing: 350 m³
Overhead Contact Line:
Supply and installation of catenary poles and flexible gantries: 120 units
Supply and installation of catenary (simple contact line): 3.410 m
Supply and installation of earthing systems: 2.427 m