Detalhes do Projeto

REHABILITATION OF THE RAILWAY BRANCH OF THE PORT OF SINES

Client: APS – Administração dos Portos de Sines e do Algarve, S.A.
Location: Terminal XXI – ZIL3 – TCS Terminal Contentores Sines – Portugal
Execution Period: 9 Months

 

The works carried out in the railway branch of the port of Sines was part of the intervention to broaden the capacity of the reception / expedition hub, giving the said branch a higher capacity and performance and allowing for the operation of 750 m long trainsets. The main alterations to be introduced were the re-adjustment of the western side of the reception / expedition hub – in particular Line I that was given a length compatible with the operation of 750 m long trainsets; the creation of a 4th in the existing reception / expedition hub, parallel to Line III, with capacity to operate trainsets with the said length; the creation of the necessary infrastructure to allow, in the future, for the construction of a 5th Line, parallel to Line IV; the creation of a new access line that, beginning at the existing one will make it possible to connect to the new loading / unloading zone of the existing Terminal ; the creation of a connection the east end of the reception hub and the new access line; the creation of a new reversion end to replace the existing one; the creation of a new siding end to park rolling stock; and also the insertion of a TJD (transversal double junction) allowing for the connection between (siding / reception hub) and the future access lines and reversion line, as well as to the siding line.

Main work quantities:

Earthworks and Paving:
Earthworks: 97.930 m³
Sub-ballast: 3.650 m³

Drainage:
Ditches, trenches, half-round, drains and collectors: 8.935 m
Drainage boxes and discharge outlets: 80 units

Accessory Works:
Landscaping – Hydroseeding in two applications: 14.800 m2
Fences in variable wire mesh: 1.200 m
Public lighting networks and lighting columns / towers; Infrastructure: 2.200 m
Reinforced concrete walls and track buffer stop: 365 m³

Signage and Safety Equipment:
Trenches and crossings with cable trays in prefabricated gutter / PEHD pipes: 4.960 m
Earthing network: 3.980 m

Railway track:
Track UIC 54/ wood sleeper removal: 1.008 m
Supply and laying of track with 54E rail and multi-purpose monoblock sleepers: 2.211 m
Supply and laying of railroad switchers: 7 units
Supply of ballast and track ballasting: 12.000 tons
Heavy mechanical tamping, including dynamic stabilisation in open track: 6.194 m
Execution of aluminothermic welding in open track and TSD (track switching devices): 376 units
Levelling of long welded bar: 12.012 m

Track Electrification:
Civil Works: Concrete in foundation footings and poles sealing: 350 m³

Overhead Contact Line:
Supply and installation of catenary poles and flexible gantries: 120 units
Supply and installation of catenary (simple contact line): 3.410 m
Supply and installation of earthing systems: 2.427 m

 

Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.

Strictly Necessary Cookies

Strictly Necessary Cookie should be enabled at all times so that we can save your preferences for cookie settings.

3rd Party Cookies

This website uses Google Analytics to collect anonymous information such as the number of visitors to the site, and the most popular pages.

Keeping this cookie enabled helps us to improve our website.