TUNNEL OF THE METRO OF LIMA STAGE 1B (CONSTRUCTION)

Client: CONSORCIO CONSTRUCTOR M2 LIMA
Location: Lima – Peru
Execution Period: 15 Months

 

Contract work consisting of excavation, application of primary support and definitive support for 1.159 m of tunnel with a variable section of 68,4 m2 to 158,7 m2 and a 24.5 m deep shaft with a diameter of 18 m and a section of 246 m2. The total estimated excavation volume is 111.000 m³, the estimated concrete volume is 14.000 m³ and the amount of steel to be applied is 786 tons.