SETÚBAL INTEGRATION DESIGN
PM-4 BUILDING AT THE INDUSTRIAL POLE OF PORTUCEL IN MITRENA

Owner: About the Future – Empresa Produtora de Papel, S.A.
Site: Mitrena – Setúbal – Portugal
Conclusion year: 2009

 

Construction of a industrial building with about 30.000 m2.

Execution of the foundations with pile head blocks, reinforced concrete structure covered with pillars, beams and slabs.

Execution of construction finishing’s (masonry, plaster, stucco, sawmills, carpentry, doors, coverings and paintings, etc.). Metal roof line with thermo-isolated plate, concrete blocks façades and pre-assembled lined panels and metal panels.

The contract Job includes the execution of HVAC (heating, ventilation and air conditioning), electrical, water and sewerage installations.

 

Concrete    68.722  m³

Formwork    126.255  m²

Steel     10.386  ton