SANTA LUZIA CATCHMENT AND WATER TREATMENT PLANT
PUMPING STATIONS, PIPELINES AND ASSOCIATED RESERVOIRS

Owner: Águas do Centro, S.A.
Site: Pampilhosa da Serra – Portugal
Conclusion year: 2006

 

Civil construction, supply and mounting of equipment and electrical installations for the following works:

 

– Construction of a waste water treatment plant with boom raft pumping installed on Sta. Luzia dam.

 

Feeder pipes:

Ø 200 mm  Ductile galvanised iron tubing  7 032 ml

Ø 250 mm  Ductile galvanised iron tubing   1 205 ml

Others  510 ml

 

Reservoirs:

Execution of two chamber reservoir for supply to Pampilhosa  (2 x 300m3 = 600 m3)

Execution of two-chamber reservoir for supply to Oleiros
(2 x 500m3 = 1 000 m3)

 

Total population  22 000 hab

Maximum daily flow  4 900 m3

Maximum hourly flow   305 m3

 

Pumping stations:

 

Water intake:

Power: 2 x 43 a 76 kW

Q=63 l/s

H=53,5 a 98 mca

 

Pampilhosa Pumping Station:

Power: 2 x 37 kW

Q=22,5 l/s

H=108 mca

Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.

Strictly Necessary Cookies

Strictly Necessary Cookie should be enabled at all times so that we can save your preferences for cookie settings.

3rd Party Cookies

This website uses Google Analytics to collect anonymous information such as the number of visitors to the site, and the most popular pages.

Keeping this cookie enabled helps us to improve our website.