BYPASS TO ALCÁCER DO SAL – 2ND PHASE
RAILWAY CROSSING OF SADO AND ACCESS VIADUCTS
Client: REFER – Rede Ferroviária Nacional, E.P.
Location: Alcácer do Sal – Portugal
Execution Period: 33 months
Conclusion Year: 2010
This project consisted of the execution, in the South railway line, km 8+350 and km 11+265, Alcácer do Sal – Portugal, of the following activities:
Construction of a bridge with spans, with a length of 480 meters, metallic deck with bow-strings in the spans with a height of 26,30 meters.
Southern access viaduct with a length of 1.140 meters: 17 spans of 45 m and 10 spans of 37,5 meters.
Northern access viaduct with a length of 1.114,5 meters: 19 spans of 45 m, 6 spans of 37,5 m and 1 span of 34,75 m.
Piles Ø 1200mm (41 units): 675 m
Piles Ø 1500mm (192 units): 5.250 m
Piles Ø 2000mm (42 units): 1.380 m
Cofferdams in the river using sheet piles AU18 (4 units): 4950 m²
Cofferdams in the margins (20 units): 11.500 m²
Concrete: 64.000 m³
Steel A500: 8.700 tons
Formwork: 100.000 m²
Steel sheet and profiles: 12.000 tons