PACOTE N2 VALE – SÃO LUIS DO MARANHÃO INSTALLATION OF CONTINUOUS FLIGHT AUGER PILES

Client: Vale S.A.
Location: São Luis – Maranhão – Brasil
Execution Period:  6 months

 

Installation of the foundation of the track beams of two new ore stackers / reclaimers.

Amount of work

400 mm CFA piles 700 m

500 mm CFA piles 25,000 m

600 mm CFA piles 9,900 m

Static load tests on continuous flight auger piles 10 un