Detalhes do Projeto

EXPANSION OF THE DESALINATION PLANT OF PORTO SANTO

Client: IGA – Investimentos e Gestão da Água, S.A.
Location: Porto Santo – Madeira – Portugal
Execution Period: 9 Months

 

Expansion and remodelling of the capture gallery 4, expansion and rehabilitation of the building of the desalination central , installation of new equipment in capture galleries 1 and 2. The project included civil works, waterproofing, coating / cladding, electrical installations, air conditioned, fire detection, ducts, lifting stations and desalination equipment.

Lifting station (capture galleries 1 and 2):

Number of pumps 4 (+1) un
Power 4 x 2 kw 8 kw
Flow 4 x 5 l/s 20 l/s
H = 18 mca