DOURO LITORAL ROAD CONCESSION
SEIXO ALVO TUNNEL

Client: DLACE – Douro Litoral, ACE
Location: Seixo Alvo – Vila Nova de Gaia – Portugal
Execution Period: 18 Meses

 

Execution of a road tunnel as part of the Douro Litoral concession, executed using the methodologies “NATM” and “Drill and Blast”

Length 2×300 m
2 Galleries
Section : 148 m2
Width : 15 m

Open sky excavation: 175.000 m³
Excavation ZG3: 56.400 m³
Excavation ZG2: 17.700 m³
Excavation ZG1: 9.456 m³

Forepoling: 30.000 m
Steel in arches: 376 tons
Rockbolting: 24.000 m
Shotcrete: 51.000 m2
Definitive concrete coating: 10.500 m³
Steel A500: 1.100 tons

 

Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.

Strictly Necessary Cookies

Strictly Necessary Cookie should be enabled at all times so that we can save your preferences for cookie settings.

3rd Party Cookies

This website uses Google Analytics to collect anonymous information such as the number of visitors to the site, and the most popular pages.

Keeping this cookie enabled helps us to improve our website.