Detalhes do Projeto

PISÃO DAM AND RESPECTIVE ROAD NETWORK

Client: EDIA – Empresa de Desenvolvimento e Infra-estruturas do Alqueva, S.A.
Location: Beringel – Beja – Portugal
Execution Period: 19 Months

 

Construction of an earth dam for an hydrographic basin of 49 km2, zoned profile type, maximum height above the bed of 13,80 m, capping benchmark of 157,50 m, development of the capping 454 m, capping with a width of 8 meters.
Construction of the hydroelectric power plant for an annual average turbine volume of 37,74 hm3, average production of 2,05 GWh/year, composed of a loading chamber of 100 m3, diversion conduit with a length of 200 m and Ø 1.200 mm.
Hydroelectric power plant with a turbine-power generator with an installed capacity of 800 kVA, dimensioning flow of 2,85 m3/s and 25,5 m useful drop and a restitution canal to Pisão reservoir.

Backfill: 160.000 m3
Dam volume: 8.500.000 m3

 

Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.

Strictly Necessary Cookies

Strictly Necessary Cookie should be enabled at all times so that we can save your preferences for cookie settings.

3rd Party Cookies

This website uses Google Analytics to collect anonymous information such as the number of visitors to the site, and the most popular pages.

Keeping this cookie enabled helps us to improve our website.