Detalhes do Projeto

SUPPLY TO CHELIFF – KERRADA – LOT 3.1
WATER SUPPLY TO THE CITIES OF MOSTAGANEM, ARZEW AND ORAN – ALGERIA

Client: Ministère des Ressources en Eau
Agence Nationale des Barrages et Transferts (ANBT)

Conclusion Year: 2010

 

This project consisted in an hydraulic work of 89.2 km long water headrace, with 2 large storing reservoirs, pumping station, including the design and construction of pipe plant located in Fournaka.

Relevant data:

Excavation/Landfills 2 169 079 m3
Formwork: 325 000 m2
Concrete: 195 000 m3
Steel: 19 000 ton

– Reinforced and pre-stressed concrete steel-core ducts:
DN 2200 mm: 6 342 m
DN 2000 mm: 46 084 m
DN 1800 mm: 17 876 m

– Steel ducts
DN 2000 mm: 14 325 m

– Ductile cast iron ducts:
DN 1400 mm: 4 618 m

– Mostaganem Reservoir:
Capacity: 120 000 m3
Construction area: 21 054 m2

– Oran Reservoir:
Capacity: 300 000 m3
Construction area: 56 143 m2

– Pipe plant:
Layout area: 120 000 m2
Total building area: 42 000 m2
Production: 4 km pipe/month

– Pumping Station:
Head: 64 m
Power: 3,6 MW
Flow: 4 m3/s

 

Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.

Strictly Necessary Cookies

Strictly Necessary Cookie should be enabled at all times so that we can save your preferences for cookie settings.

3rd Party Cookies

This website uses Google Analytics to collect anonymous information such as the number of visitors to the site, and the most popular pages.

Keeping this cookie enabled helps us to improve our website.