This work comprised the execution of rehabilitation and expansion works of the existing tug boats pier, in which the following activities were integrated:

  • Demolition of existing structures;
  • Landfilling and paving works: 4 500 m2;
  • Sheet piles curtain “AZ44-700” with 24 meters wide;
  • Reinforced concrete works: Pier top beam and ancillary works: 308 m3;
  • Supply and installation of pier accessories:
    • Fenders SPC 600 – 7,50×1,20m: 14 units;
    • Fenders SC-Fenders (300x250x6000): 18 units;
    • Bollards T-Bollard 50 ton: 9 units;
  • Electrical and water supply infrastructures;
  • Rehabilitation of the existing Dredging Quay structure;
  • Rehabilitation of the existing Tugboats Quay structure.
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.

Strictly Necessary Cookies

Strictly Necessary Cookie should be enabled at all times so that we can save your preferences for cookie settings.

3rd Party Cookies

This website uses Google Analytics to collect anonymous information such as the number of visitors to the site, and the most popular pages.

Keeping this cookie enabled helps us to improve our website.