Detalhes do Projeto

MUNDI RESIDENTIAL BUILDING INSTALLATION OF BORED PILES AND DIAPHRAGM WALL

Client: Gafisa S.A.
Location: Espaço Cerâmica – São Caetano do Sul – São Paulo – Brasil
Execution Period: 3 months

 

Peripheral containment with diaphragm wall and deep-foundation bored piles
using stabilized fluid.

 

Amount of work:

40 cm diaphragm wall: 5.580 m²

Bored piles:

Ø 700 and 900 mm piles 770 m

Ø 1,000 and 1,300 mm piles 1,580 m

Ø 1,400 and 1,600 mm piles 1,300 m

 

Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.

Strictly Necessary Cookies

Strictly Necessary Cookie should be enabled at all times so that we can save your preferences for cookie settings.

3rd Party Cookies

This website uses Google Analytics to collect anonymous information such as the number of visitors to the site, and the most popular pages.

Keeping this cookie enabled helps us to improve our website.