Detalhes do Projeto

MONOTRILHO CONSORTIUM – INCORPORATION OF SUBWAY LINE 17 / SPINSTALLATION OF BORED PILES WITH STABILIZING MATERIAL

Client: Consórcio Andrade Gutierez/ CR Almeida
Location: Av. Jornalista Roberto Marinho – São Paulo – Brasil
Execution Period: 24 months

 

Installation of large-diameter deep foundation piles adapting the drilling technology to the heterogeneity of the drilled soils, including a crack in the topmost 8 m (thus driving a metal casing) and bedrock and streamlining procedures according to the usual constraints associated with works carried out in urban areas.

Amount of work:

Ø 1.000m piles: 240 m
Ø 1.200mm piles: 6.400 m
Ø 1.500mm piles: 5.348 m
Ø 1.600mm piles: 120 m
Ø 1.800mm piles: 78 m

Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.

Strictly Necessary Cookies

Strictly Necessary Cookie should be enabled at all times so that we can save your preferences for cookie settings.

3rd Party Cookies

This website uses Google Analytics to collect anonymous information such as the number of visitors to the site, and the most popular pages.

Keeping this cookie enabled helps us to improve our website.