Detalhes do Projeto
MONOTRILHO CONSORTIUM – INCORPORATION OF SUBWAY LINE 17 / SP – INSTALLATION OF BORED PILES WITH STABILIZING MATERIAL
Client: Consórcio Andrade Gutierez/ CR Almeida
Location: Av. Jornalista Roberto Marinho – São Paulo – Brasil
Execution Period: 24 months
Installation of large-diameter deep foundation piles adapting the drilling technology to the heterogeneity of the drilled soils, including a crack in the topmost 8 m (thus driving a metal casing) and bedrock and streamlining procedures according to the usual constraints associated with works carried out in urban areas.
Amount of work:
Ø 1.000m piles: 240 m
Ø 1.200mm piles: 6.400 m
Ø 1.500mm piles: 5.348 m
Ø 1.600mm piles: 120 m
Ø 1.800mm piles: 78 m