Detalhes do Projeto

BYPASS TO PONTA DO SOL

Client: Regional Government of Madeira; Regional Secretariat of Social Equipment and Transports
Location: Ponta do Sol – Madeira – Portugal
Execution Period: 25 Months

 

Construction of a road tunnel with a length of approximately 2.700 meters, with a excavation cross section ranging from 75 m2 to 101 m2, comprising excavation, provisional and definitive coating, portals, drainage network, paving, supply and assembling of horizontal and vertical signage, lighting, ventilation and firefighting network.

Excavation: 216.737 m3
Concrete: 24.150 m3
Steel rod and welded wire mesh: 362.540 kg
“Swellex” type anchors: 13.406 unit
Metallic sheets and arches: 481.673 kg
Pavements: 22.548 m2